New Geothermal Power Station for Kawerau
Client Name: Mighty River Power
Strategy & Planning: no
Project Delivery: yes
Design: no
Technical Services: yes
Mighty River Power’s new Kawerau geothermal power station is fully operational ahead of time, under budget and capable of generating at a higher than expected capacity of 100MW.
The $300 million Kwerau project was the largest single geothermal development in New Zealand for more than 20...
Nga Awa Purua Geothermal Power Station
Client Name: Mighty River Power
Strategy & Planning: no
Project Delivery: yes
Design: no
Technical Services: no
Mighty River Power’s new Nga Awa Purua geothermal power station is its second geothermal development. The $430M geothermal power station has a capacity of 140MW and connects into Transpower’s existing 220kV transmission grid.
Nga Awa Purua houses the largest single shaft...