Projects

Whakamaru North Switching Station

Whakamaru North Switching Station Whakamaru North Switching Station

Project Overview:

The Whakamaru North project is part of the North Island Grid Upgrade Project – currently the largest electricity transmission project to be undertaken in New Zealand since 1960.

While Whakamaru North was home to an existing switchyard, significant upgrades were required to accommodate the higher level project plans. A new switchyard was also required to be built 800 metres north of the original switchyard. An extension of the existing switchyard and a short tie-line was included to effectively transfer power between the two switchyards.

The inclusion of new technologies in the new switchyard, and the interfacing of the new equipment with the existing switchyard, added a level of complexity to this project for everyone involved. Establishing a seamless interface between both substations also provided some new and interesting challenges as well.

Edison Delivery:

Edison was engaged by Transpower to effectively see through the successful electrical installation and commissioning of the Whakamaru North project – including the existing switchyard extension and the new switchyard.

Edison was also engaged as the commissioning engineer for Whakamaru to commission the overall NIGUP project comprising the two new 220kV circuits from Whakamaru to Pakuranga.

The key priority for the team at Edison was to flesh out and resolve technical issues as they arose. This included liaising with the numerous stakeholders. After spending time focusing on how to resolve all technical issues at the two sites, the project was able to be implemented relatively smoothly.

Due to the highly complex nature of this particular project, Edison was also very involved in the day-to-day implementation including weekly site visits, resolving on-site challenges and coordinating with the various stakeholders throughout the project.

As a result, the project was completed safely and efficiently, without any unforeseen hold-ups or difficulties.

The lead Edison consultant on this project was an integral part of the team and was a key part of Transpower meeting their project goals.

Alan Stephenson, Transpower

Speak to our team about your next project

Richard Kingsford

General Manager Design & Advisory

Hamilton

David Webb

General Manager Project Delivery

Christchurch

Jonathan Buell

Regional Manager

Auckland

Mark Vincent

Regional Manager

Hamilton

Mark Lewis

Regional Manager

Tauranga

Gerald Dignan

Regional Manager

Wellington